Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits

정답: B,E
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)

정답: B,E,F
Why might a RAD approach be a better option for the test manager rather than a sequential development? 2 credits

정답: C
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV.
Defect trend (number of defects found per test run over time

정답: B
설명: (Fast2test 회원만 볼 수 있음)
As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use? 2 credits

정답: A
Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi? 1 credit

정답: A,E,G
You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit

정답: C