PMI Risk Management Professional - PMI-RMP무료 덤프문제 풀어보기
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.
정답: A
설명: (Fast2test 회원만 볼 수 있음)
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
What should the risk manager do first to understand the impact on project cost?
정답: D
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?
What should the project manager do to avoid this risk?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager ' s next step?
What should be the risk manager ' s next step?
정답: D
A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.
What should the risk manager do?
What should the risk manager do?
정답: D
A risk manager has recently been assigned to a large cross-functional project that is already underway. While reviewing existing project artifacts, the risk manager discovers that risk-planning documents are incomplete and lack key information. Several risks have already occurred, and the project manager requests response guidance.
What should the risk manager do?
What should the risk manager do?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
The project manager leading a company ' s digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
정답: C,D
설명: (Fast2test 회원만 볼 수 있음)
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
정답: D
설명: (Fast2test 회원만 볼 수 있음)
A risk manager is overseeing the construction of a new office building and finds that some risks were underestimated in their impact on the project timeline and budget. The risk manager is reassessing the current risk levels to prevent further escalation.
Which two actions should the risk manager take? Choose two.
Which two actions should the risk manager take? Choose two.
정답: B,E
설명: (Fast2test 회원만 볼 수 있음)
A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed?
(Choose two.)
(Choose two.)
정답: A,C
설명: (Fast2test 회원만 볼 수 있음)