Microsoft Managing Projects and Portfolios with Microsoft PPM - 070-348무료 덤프문제 풀어보기

HOTSPOT
You are the project manager for a real estate management company. You are using
Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
정답:
HOTSPOT
You are a project manager for an organization that uses visibility projects in Microsoft PPM.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
정답:

Explanation:

References:
https://support.office.com/en-gb/article/Publish-a-project-b4c7593d-0844-4d28-bf2c-
5ddff2498e33
HOTSPOT
You create a new project plan. You plan to take a snapshot of the project before and after the project start date.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
정답:

Explanation:

The first baseline happens after the planning stage of the project. It is a snapshot of the planned timescales.
At the start of a project, when the manager has all the tasks in place, the people are assigned and the money is budgeted, he creates a baseline of data for his project so that he can measure its progress.
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-
7E775482-AC84-4F4A-BBD0-592F9AC91953
HOTSPOT
You are a project manager for an organization that is using Microsoft PPM to manage projects. Projects are staffed using the enterprise resource pool.
You assign a resource to a task and set the value of Work hours to 10. You assign no overtime hours.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
정답:
You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.
Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.
You need to configure Microsoft PPM.
What should you do?

정답: A