Microsoft Managing Projects with Microsoft Project 2013 - 074-343무료 덤프문제 풀어보기

You update a schedule that you are managing by using Microsoft Project.
After the update, you observe that many of the resources in the schedule are overallocated.
You need to resource level the schedule without changing the current projected finish data for the project.
Which three actions will achieve the goal? Each correct answer presents part of the solution.

정답: C,D,E
You are a project manager for a company that is based in New York and London. The company uses Project Professional 2013.
Teams from both offices are working together on a project. Since the two offices are located in different regions, the teams have separate company holiday schedules and working times.
You need to ensure that the effort for each resource and task is set up properly in the calendar.
You want to achieve this goal by using the least amount of time and effort.
What should you do?

정답: B
You are a project manager who uses Project Standard 2013.
Your manager wants you to plan an office move. You have a project schedule from a prior office move named "OfficeMove.mpp" and you want to use this project to assist in planning the current office move.
In the fewest steps possible, you need to create your new project schedule based on the old project schedule.
What should you do?

정답: B
You work as a project manager for a construction company that uses Project Professional
2013.
You have created your work breakdown structure (WBS) and are adding resources to your tasks. However, one of your tasks requires multiple resources. You have the name of the project's lead support individual, and you have been provided with the equivalent of three full-time support resources. These three resources are not named individuals but are part of a group.
The actual individuals from this group will change based on coverage schedules.
The resources have the following cost structures:
* The lead is billed out at S175/hour.
* The group resources are billed out at $140/hour.
You need to add these resources to the schedule and track your project costs.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

정답: C,D
You manage a project by using Project Professional 2013.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder's request.
What should you do?

정답: B
You manage a project by using Project Professional 2013.
The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.
You need to solve this problem.
What should you add to the task?

정답: A
You are tracking a project schedule by using Microsoft Project. The project schedule contains a baseline.
You need to display a view that displays the slippage of the current plan as compared to the baseline for the schedule.
Which two actions will achieve the goal? Each correct answer presents a complete solution.

정답: B
설명: (Fast2test 회원만 볼 수 있음)
Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

정답: B,C