You have an absence plan that has mistakenly run for the following leave year for all employees. The absence leave year runs from January the 1st. The current balance calculation date is 31 January 2018 and you want to roll it back to the 31 December 2017.
What date should you enter in the Effective Date parameter for the Withdraw Accruals and Balances process to achieve this?
What date should you enter in the Effective Date parameter for the Withdraw Accruals and Balances process to achieve this?
정답: A
Your customer has a rule for Maternity entitlements according to which the qualification date is on the absence start date if actual dates are entered or if it is not entered, then the qualification date needs to be the event date (actual if available, or else, the planned date).
Which formula should you use in the absence plan setup to achieve this?
Which formula should you use in the absence plan setup to achieve this?
정답: E
Which three statements about the "Selected dates" frequency are true?
정답: B,C,F
You defined a two-year rolling backward term in your qualification plan with UOM as calendar days. You set up bands that entitle workers to 50-days absence at payment percentage 100% and an additional 50 days at payment percentage 50%.
A worker took an absence for 92 days, from May 1, 2015 to July 31, 2015. The same worker schedules another absence using the same plan July 1, 2016 to July 30, 2016 for 30 days.
What is the available entitlement for this absence?
A worker took an absence for 92 days, from May 1, 2015 to July 31, 2015. The same worker schedules another absence using the same plan July 1, 2016 to July 30, 2016 for 30 days.
What is the available entitlement for this absence?
정답: B
Your customer has many absence entries in the system that they want to withdraw using HDL.
Which command should you pass in the load file to withdraw all of these entries?
Which command should you pass in the load file to withdraw all of these entries?
정답: A
When assigning work schedules via Manage Work Schedule Assignment Administration task, which level has the highest priority and which level the lowest?
정답: D
A customer set up the certification requirement for an absence. After scheduling the absence for a subordinate, the line manager wants to add a certification requirement as an action item, but is unable to do it.
Identify the reason for this.
Identify the reason for this.
정답: D
Which statement is correct about rate definitions?
정답: B
You need absence management to integrate with Fusion Payroll.
What should you set up in Absences to implement this?
What should you set up in Absences to implement this?