Oracle EBS R12: Advanced Supply Chain Planning - 1Z0-244무료 덤프문제 풀어보기

Identify the three steps that a planner can perform during Net change Simul-ation On-line planning.

정답: A,E,F
The planning engine gives an exception message "Items with no activity." When does this exception appear?

정답: B
Identify the three correct statements about the setups required to enable pegging within an ASCP plan.

정답: B,D,E
After a plan completes successfully, the planning SuperUser wants to be Informed If there Is a quantity excess of 7500 for a specific group of items. What would be your recommendation?

정답: D
Your client is using Global Forecasts. The client's Planning Manager states that Sales Order consumption is not working correctly. Identify two possible causes.

정답: A,C
Which are the four pegging modes available for a user to set up in combination with the MSC: Use FIFO Pegging profile option?

정답: D,E,F,H
The table In the Exhibit.

shows Gross Requirements, Scheduled Receipts, and Project Available Balance for Item A across a five-day planning horizon. The Beginning On Hand, Lead Time, and Fixed Lot Multiplier for Item A are also provided.
What are the Planned Order Release recommendations?

정답: C
Which exception message appears when the planning engine schedules a Supply Order within a window whose size Is less than the minimum duration of the Supply Order?

정답: A
The following is the business scenario at your client site:
1) Your client manufactures goods that can be produced In alternate ways that requires flexible definition of Routings.
2) They have multiple manufacturing Organizations namely Ml, M2, and M3.
3) The future operation details of Jobs need to be stored only In Ml and M3.
4) A complete recommended path for a Job should exist and should be updatable.
Which one will be part of your solution?

정답: B