A customer is using Fusion Payables and Fusion Project Portfolio Management.
The customer has two suppliers setup with names X and Y respectively.
Supplier Y has been merged with supplier X. the supplier merge program is run from the supplier merge option in Fusion Payables and you have chosen to merge all transactions. What will happen to the supplier references on transactions related to supplier Y that are already interfaced to Fusion Project Portfolio Management?
The customer has two suppliers setup with names X and Y respectively.
Supplier Y has been merged with supplier X. the supplier merge program is run from the supplier merge option in Fusion Payables and you have chosen to merge all transactions. What will happen to the supplier references on transactions related to supplier Y that are already interfaced to Fusion Project Portfolio Management?
정답: A
Select two correct statements pertaining to project classifications on a template.
정답: C,D
Select three things the Major Axis on the Project Plan Gantt Chart timescale show when the minor axis is set to Months.
정답: A,C,E
Select the true statement related to Descriptive Flex fields and OTBI in Fusion Applications.
정답: A
설명: (Fast2test 회원만 볼 수 있음)
CORRECT TEXT
Select the correct option to fill in the blank below.
If revenue is recognized before billing, the accounting entry that gets triggered would be _________.

Select the correct option to fill in the blank below.
If revenue is recognized before billing, the accounting entry that gets triggered would be _________.

정답: A
As you implement the Project Integration Gateway, you are required to set up the integration options for exporting actual amounts. What are the two valid options for export?
정답: C,D
Select the four duties the project administrator is entitled to, by default, in Budgeting and Forecasting.
정답: A,B,C,E
Select the two options that would accurately fill in the blanks in the sentences below.
The rate sources in Fusion PPM are based on the Schedule Types specified on the Invoice and Revenue Methods. If the schedule type is Labor Schedule, Bill Rate, then a valid rate source would be ____________ or _______.
The rate sources in Fusion PPM are based on the Schedule Types specified on the Invoice and Revenue Methods. If the schedule type is Labor Schedule, Bill Rate, then a valid rate source would be ____________ or _______.
정답: C,E