Microsoft Recertification for MCSD: Application Lifecycle Management - 70-499무료 덤프문제 풀어보기
DRAG DROP
You are on the development team of your company's newly-formed Scrum team.
At the start of your first sprint, your Scrum Master tells you that you are required to
participate in the Daily Scrum or Stand-up.
You need to attend this meeting and give feedback to three important questions.
Which three questions should you answer in sequence? To answer, move the appropriate
questions from the list in the answer area and arrange them in the correct order.

You are on the development team of your company's newly-formed Scrum team.
At the start of your first sprint, your Scrum Master tells you that you are required to
participate in the Daily Scrum or Stand-up.
You need to attend this meeting and give feedback to three important questions.
Which three questions should you answer in sequence? To answer, move the appropriate
questions from the list in the answer area and arrange them in the correct order.

정답:

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server and Microsoft Lab Management (MLM) 2012.
You want to create a clone of the development test environment in your domain that will support testing patches of your software while continuing to support release testing in the existing environment.
You need to configure the environment to support network isolation.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
You want to create a clone of the development test environment in your domain that will support testing patches of your software while continuing to support release testing in the existing environment.
You need to configure the environment to support network isolation.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
정답: B,D,F
Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. All of your Team Projects use the default Scrum process template.
You create a new work item type named AcceptanceBug.
You need to ensure that work items of this type are displayed in queries for bugs.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You create a new work item type named AcceptanceBug.
You need to ensure that work items of this type are displayed in queries for bugs.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: C,D
You are the administrator for a Microsoft Visual Studio Team Foundation Server (TFS) installation at your company's headquarters.
Some of the company's development work is performed offsite at a location with slow Internet access. You set up a version control proxy at that site to lower the response time for those users.
You need to identify the cache hit ratio of the version control proxy to ensure that it meets a minimum service level.
What should you do?
Some of the company's development work is performed offsite at a location with slow Internet access. You set up a version control proxy at that site to lower the response time for those users.
You need to identify the cache hit ratio of the version control proxy to ensure that it meets a minimum service level.
What should you do?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
HOTSPOT
You are a software developer for Contoso, Ltd. Microsoft Visual Studio Team Foundation Server (TFS) manages your code and project artifacts. The root of the project is S/Contoso/Main.
You work primarily in the $/Contoso/Main/Website folder and below it. You do not want a copy of the folder $/Contoso/Main/Website/Images due to its size.
You need to maximize your workspace for efficiency by minimizing the number of files you pull from the server.
In the table below, select which folder should be mapped as cloaked and which as active. Make only one selection in each column.

You are a software developer for Contoso, Ltd. Microsoft Visual Studio Team Foundation Server (TFS) manages your code and project artifacts. The root of the project is S/Contoso/Main.
You work primarily in the $/Contoso/Main/Website folder and below it. You do not want a copy of the folder $/Contoso/Main/Website/Images due to its size.
You need to maximize your workspace for efficiency by minimizing the number of files you pull from the server.
In the table below, select which folder should be mapped as cloaked and which as active. Make only one selection in each column.

정답:

DRAG DROP
You are using Microsoft Test Manager (MTM).
Your company would like to support the Windows Server 2008 operating system for the application being tested.
You need to add Windows Server 2008 as a new value to the operating system configuration variable.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

You are using Microsoft Test Manager (MTM).
Your company would like to support the Windows Server 2008 operating system for the application being tested.
You need to add Windows Server 2008 as a new value to the operating system configuration variable.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

정답:

Your network environment is configured according to the following table:

DATA1 experiences complete hardware failure.
You restore operations on a new server. However, some users experience errors with Work Item tracking and Workspaces.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

DATA1 experiences complete hardware failure.
You restore operations on a new server. However, some users experience errors with Work Item tracking and Workspaces.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: B,C
DRAG DROP
Your team uses Microsoft Test Manager (MTM) to manage test cases.
You are creating manual test cases so that your team can run the tests as part of the test process.
You need to ensure that testers have to specify whether a test step passes or fails before they finish running the test case.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Your team uses Microsoft Test Manager (MTM) to manage test cases.
You are creating manual test cases so that your team can run the tests as part of the test process.
You need to ensure that testers have to specify whether a test step passes or fails before they finish running the test case.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

정답:

Your development team is using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CM MI) Process Improvement 6.0 process template.
You identify the high business value requirements of a project.
You need to prioritize the requirements and ensure that the updates are reflected on the TFS reports.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You identify the high business value requirements of a project.
You need to prioritize the requirements and ensure that the updates are reflected on the TFS reports.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: A,C
Your network environment is configured according to the following table:

---
Your TFS environment is configured with the following URLs:
TFS: http: //tfssrv: 8080/tfs
Reporting: http: //tfssrv/reports
SharePoint: http: //tfssrv/sites
You need to configure only the TFS URL to be the following fully qualified domain name (FQDN): http: //tfs.contoso.com.
You log on to the application-tier server. What should you do next?

---
Your TFS environment is configured with the following URLs:
TFS: http: //tfssrv: 8080/tfs
Reporting: http: //tfssrv/reports
SharePoint: http: //tfssrv/sites
You need to configure only the TFS URL to be the following fully qualified domain name (FQDN): http: //tfs.contoso.com.
You log on to the application-tier server. What should you do next?
정답: D
You are using Microsoft Test Manager (MTM) to perform exploratory testing.
You need to insert an image into the comment area for the test run.
What are two possible ways to accomplish this goal? (Each correct answer presents a complete solution. Choose two.)
You need to insert an image into the comment area for the test run.
What are two possible ways to accomplish this goal? (Each correct answer presents a complete solution. Choose two.)
정답: B,C
You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Agile Software Development process template. SharePoint integration and reporting are enabled.
You want to assess your team's testing effort.
To do this, you need to:
Identify how much testing has the team completed,
Determine whether the team is likely to finish the testing on time,
Identify how many tests have passed, failed, or blocked, and
Identify how many tests are left to be run.
What should you do?
You want to assess your team's testing effort.
To do this, you need to:
Identify how much testing has the team completed,
Determine whether the team is likely to finish the testing on time,
Identify how many tests have passed, failed, or blocked, and
Identify how many tests are left to be run.
What should you do?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
Your client has a Microsoft Visual Studio Team Foundation Server (TFS) 2013 installation with Lab Management. The client uses the Microsoft stack to test tools. The testing team uses manual and automated testing.
You are testing the following two scenarios of Acceptance Criteria for the story:
Scenario 1
"Given a non-rewards member goes to the reservations site,
when entering Tampa, FL, as the city
and an arrival date of 12/25/2014
and a departure date of 1/1/2015,
then the website should show a hotel room with the price of $225 per night
and another hotel room with a price of $199 per night."
Scenario 2
"Given a non-rewards member goes to the reservations site,
when entering Denver, CO, as the city and an arrival date of 1/25/2015 and a departure date of 1/27/2015, then the website should show a hotel room with the price of $145 per night and another hotel room with a price of $186 per night."
You need to create a flexible manual test case that can accommodate the two scenarios. The test should include three parameters, one for the city, one for the trip dates, and one for the results.
What should you do?

You are testing the following two scenarios of Acceptance Criteria for the story:
Scenario 1
"Given a non-rewards member goes to the reservations site,
when entering Tampa, FL, as the city
and an arrival date of 12/25/2014
and a departure date of 1/1/2015,
then the website should show a hotel room with the price of $225 per night
and another hotel room with a price of $199 per night."
Scenario 2
"Given a non-rewards member goes to the reservations site,
when entering Denver, CO, as the city and an arrival date of 1/25/2015 and a departure date of 1/27/2015, then the website should show a hotel room with the price of $145 per night and another hotel room with a price of $186 per night."
You need to create a flexible manual test case that can accommodate the two scenarios. The test should include three parameters, one for the city, one for the trip dates, and one for the results.
What should you do?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server.
Version control is configured with one project collection and two team projects. Some users use 2010 and 2012 clients, such as Visual Studio and Team Explorer Everywhere.
You need to ensure that users will be prompted by, and can satisfy, the comments check-in policy when using both 2010 and 2012 clients.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Version control is configured with one project collection and two team projects. Some users use 2010 and 2012 clients, such as Visual Studio and Team Explorer Everywhere.
You need to ensure that users will be prompted by, and can satisfy, the comments check-in policy when using both 2010 and 2012 clients.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: A,D