Microsoft Managing Programs and Projects with Project Server 2013 - 74-344무료 덤프문제 풀어보기

Your organization uses Project Server 2013. You are the project manager of a schedule.
Team Members send you emails with their percentage complete on their assignments.
Your organization only uses the following two percentages for tracking tasks:
- 50% for tasks that are started
- 100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

정답: C,D
You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

정답: A,B
You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?

정답: A
You are a portfolio manager for an organization that uses Project Server 2013.
You plan to create weekly status project reports for your executive team. You want to publish your report only once in Project Web App (PWA). Users must be able to fully interact with the report by adding or excluding fields and by changing the rows or columns fields.
You need to create a report that meets these requirements.
What should you do?

정답: D
You are an area project manager who uses Project Server 2013.
You are aligning and planning your team's availability against existing and proposed projects.
You need to estimate your team members' work load for future time periods against projects that have not completed a work breakdown structure (WBS) yet. You need to account for both existing and planned projects.
What should you do?

정답: D
You are a project manager for an organization that uses Project Server 2013.
After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks.
You need to link the risks to their related tasks.
What should you do?

정답: B
You are a project manager for an organization that uses Project Server 2013.
Your team members update their task status.
You need to see how these updates impact your project before you approve the tasks.
What should you do?

정답: D
Your organization uses Project Online for project portfolio selection. The business drivers and priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may solve the same business need. For example, the selection for a Customer Relationship Management system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources and that no repetitive efforts exist in the portfolio selection.
What should you do?

정답: C
You are a project manager in an organization that uses Project Server 2013. You manage two projects named Proj1 and Proj2.
You create a deliverable dependency between both projects by taking the following actions:
- You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1. The Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
- On Proj2, you associate a dependency that has a milestone named Milestone2 to the Deliverable1.
After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1 ahead by five days.
You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

정답: A,C
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?

정답: D