Adobe Workfront Project Manager Certified Professional - AD0-E911무료 덤프문제 풀어보기
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
Which field should the manager reference to view all task assignees?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
A user wants to notify a team of a new work request for them to work on.
Where would the user set the team so they are notified of the new work request?
Where would the user set the team so they are notified of the new work request?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?
Which action should the stakeholder take to log the risk?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
In the approval path shown below, which Project Status will the Project be if rejected?
정답: A
설명: (Fast2test 회원만 볼 수 있음)
A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
A project manager is looking to create a task that must take place from September 10th through September 17th of this year.
Which action must be taken?
Which action must be taken?
정답: A
설명: (Fast2test 회원만 볼 수 있음)
Which two statements are true about Groups and Teams? (Choose two.)
정답: B,C
설명: (Fast2test 회원만 볼 수 있음)
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
Which date type would the project manager utilize?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
A project owner creates a project with the Schedule Mode set to Start Date.
Which task constraint is the default when creating new tasks in this scenario?
Which task constraint is the default when creating new tasks in this scenario?
정답: B
설명: (Fast2test 회원만 볼 수 있음)