What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.
NOTE: There are 3 correct answers to this question.
정답: B,D,E
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
What could be the reason for this?
정답: D
You staff a resource to a project.
Where is the default authorization for the resource defined?
Where is the default authorization for the resource defined?
정답: B
Where can you use the BCV report in SAP PPM?
NOTE: There are 3 correct answers to this question.
NOTE: There are 3 correct answers to this question.
정답: A,B,C
Which of the following are basic parts of SAP innovation management?
NOTE: There are 2correct answers to this question.
NOTE: There are 2correct answers to this question.
정답: B,C,E
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.
How do you move bucket A including the items to bucket p2.
정답: B
Which customizing activity do you use to integrate capacity planning of an item with financial planning?
정답: D
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
Which reporting tool do you use?
정답: B
How can you trigger a workflow for a portfolio item?
NOTE: There are 2 correct answers to this question.
NOTE: There are 2 correct answers to this question.
정답: C,D