SAP Certified Application Associate - SAP S/4HANA Project Systems - C-TS412-1909무료 덤프문제 풀어보기

The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.
What planning method for basic dates do you use ?

정답: D
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.

정답: A,C
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question

정답: A,C,D
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

정답: C,D
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

정답: C,D,E
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

정답: C
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

정답: A,C,E
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question

정답: A,D
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

정답: A,C
How can you record external service activities with service master data? Note: There are 2 correct answers to this question

정답: B,D