SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - C-TS422-1809무료 덤프문제 풀어보기

A planner updated a production order status from partially confirmed "PCNF" to technically completed
"TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:

정답: B
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics?
There are 3 correct answers to this question.
Response:

정답: A,B,D
Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
There are 3 correct answers to this question.
Response:

정답: A,B,D
What are attributes of the SAP S/4HANA Simplification list?
There are 3 correct answers to this question.
Response:

정답: A,C,E
Which advanced functionality has been embedded in SAP S/4HANA?
There are 3 correct answers to this question.
Response:

정답: A,B,E
How can you limit the number of master data objects to be created when the manufacturing process is the same for many different products?
Please choose the correct answer.
Response:

정답: A
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:

정답: B,C,E
You produce your material based on a forecast derived from historical sales and expect it to be in inventory when your customer orders. If customers order more that the forecasted quantity, you want to increase production to try to meet the extra demand.
Which is the appropriate planning strategy to use?
Response:

정답: A
Which task list types can have parallel sequences?
There are 2 correct answers to this question.
Response:

정답: C,D
Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:

정답: B,D