SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing - C_P2W22_2504무료 덤프문제 풀어보기
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
정답: B,C
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
정답: B,C
You are a consultant on an SAP S/4HANA Cloud greenfield project.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
정답: A,D
When working with the material status, for which business areas can you set a warning message?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
정답: B,C
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
정답: A,C
Which options do you have to exclude Advanced Planning materials from the standard MRP run in SAP S/4HANA?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
정답: A,B
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
정답: C,D
You want to create a production order.
What methods can you use?
Note: There are 2 correct answers to this question.
What methods can you use?
Note: There are 2 correct answers to this question.
정답: A,D
What is a work center hierarchy?
정답: C