PECB ISO 21502 Lead Project Manager - ISO-21502-Lead-Project-Manager무료 덤프문제 풀어보기
What is an advantage of using ISO 21502?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
What is the purpose of post-project activities?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
Among others, how can the project oversight be done?
정답: A
Which of the following belongs to adaptive changes?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
Who is responsible for maintaining project governance?
정답: B
설명: (Fast2test 회원만 볼 수 있음)
Which of the following, among others, is a responsibility of the work package leader?
정답: A
설명: (Fast2test 회원만 볼 수 있음)
Which of the following situations indicates a hope creep?
정답: A
설명: (Fast2test 회원만 볼 수 있음)
According to ISO 21502, what is the purpose of managing delivery?
정답: C
설명: (Fast2test 회원만 볼 수 있음)
Scenario:
Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture's suppliers of wood.
Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.
Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.
A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.
Question:
Tom asked the project team to perform tasks in the predetermined order, regardless of resource shortages.
What rule did Tom follow in this case?
Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture's suppliers of wood.
Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.
Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.
A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.
Question:
Tom asked the project team to perform tasks in the predetermined order, regardless of resource shortages.
What rule did Tom follow in this case?
정답: C
설명: (Fast2test 회원만 볼 수 있음)