You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

정답: D
설명: (Fast2test 회원만 볼 수 있음)
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

정답: A
설명: (Fast2test 회원만 볼 수 있음)
You are the project manager for the GHY Project. This project has stakeholders, both internal and external, that need to receive performance reports from you on a regular basis. You have decided that in addition to emailing the weekly performance report, you will also keep the performance reports available on your secured project management Website. The Website is an example of what type of communication reporting?

정답: D
설명: (Fast2test 회원만 볼 수 있음)
Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

정답: D
설명: (Fast2test 회원만 볼 수 있음)
A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work.
However, which of the following statements most accurately describes this parametric estimate assumption?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

정답: C
설명: (Fast2test 회원만 볼 수 있음)