ASIS Physical Security Professional - PSP무료 덤프문제 풀어보기

Determine the correct formula and date for the late start for Activity 9001.

정답: A
설명: (Fast2test 회원만 볼 수 있음)
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

정답: A
What is the result of a forward pass calculation?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
Which of the following is least likely to affect the criticality of resources in resource planning process?

정답: C
Estimate to complete (ETC) is __________________.

정답: C
설명: (Fast2test 회원만 볼 수 있음)
What is the cycle time?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
The project team must communicate the project plan, goals and objectives to all stakeholders to ensure the stakeholders understand the plan, goals and objectives and then continue this communication throughout the project life Which statement below would stakeholders NOT be expected to contribute?

정답: D
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot
[56.64 cubic meter] column?

정답: C
설명: (Fast2test 회원만 볼 수 있음)
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

정답: A
설명: (Fast2test 회원만 볼 수 있음)