The software development company has recently been awarded a large contract to create a new animation software program. This will require the company to move into a new office complete with production facilities twice their current size. The schedule is tight for this new project. The new facility is behind schedule with the cubicles and network wiring on pace to finish three weeks late. If this can't be done on time and will slip three weeks, the company has decided there is nothing it can do, and it will simply deal with the consequences. This is an example of what type of risk response?

정답: D
A multinational organization is centralizing its IT infrastructure, which is spread across 16 countries. The organization will embark on a transformation journey that encompasses three main areas:
1. Assessing which technology/tooling should be retained for the target data center.
2. Establishing a common set of processes supporting the new way of
delivering services.
3. Revising human resources (HR) processes to account for the new
improved services for employees in the various countries.
The assigned program manager is preparing the business case for the program. Which document should be present in the program manager's business case?

정답: A
Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

정답: D
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?

정답: C
A company very new to program management is working on a pilot program. The program manager of this pilot program will encounter many improvement opportunities throughout the program life cycle. How should the program manager address the need for continuous improvement throughout this pilot program?

정답: B
설명: (Fast2test 회원만 볼 수 있음)
You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?

정답: C
Which of the following is not a phase of program life cycle?

정답: B
A program manager is leading a program to upgrade an IT system. During a weekly program status review meeting, the program manager noticed that one of the projects is behind schedule.
The project manager explains that the reason for the delay is due to technical issues. The project manager reported that the operations team for the existing legacy system are not providing enough support or clarifications. What should the program manager do?

정답: D
설명: (Fast2test 회원만 볼 수 있음)