(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)
정답: B
설명: (Fast2test 회원만 볼 수 있음)
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
정답: C,D
설명: (Fast2test 회원만 볼 수 있음)
Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
정답: B,D
설명: (Fast2test 회원만 볼 수 있음)
(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))
정답: C
설명: (Fast2test 회원만 볼 수 있음)
If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
정답: A,B
설명: (Fast2test 회원만 볼 수 있음)
(Please select the one answer in which the mentioned documents are in the correct order (hierarchy), as mentioned in the standard Contract Agreement form of the FIDIC Silver Book (edition 1999).)
정답: B
설명: (Fast2test 회원만 볼 수 있음)