SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021무료 덤프문제 풀어보기

Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?

정답: B,D,E
Which of the project definition in project management must be filled before you can release a project?

정답: B
You want to distribute capacity requirements in a project management project?
How can you distribute the values? NOTE: There are 3 correct answers to this question

정답: B,C,E
What influences whether an items is displayed in a specific dashboard scope? NOTE: There are 3 correct answers to this question

정답: A,C,D
How can you trigger a workflow for a portfolio item? NOTE: There are 2 correct answers to this question.

정답: B,C
What are dashboard alerts calculations based on?

정답: A
Your client wants to add additional checklist items to a project that has already began.
They want to control the items separately as unplanned.
Which setting must you make in customizing?

정답: D
You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.
What could be a reason for the system behavior?

정답: B
For which of the following object types can you define questionnaires? NOTE: There are 2 correct answers to this question

정답: C,D