Microsoft Dynamics AX 2012 R2 Project - MB6-700무료 덤프문제 풀어보기
You generate project quotation lines based on a work breakdown structure. Which event occurs when a quotation line is modified?
정답: B
Which statement about the effective labor rate (ELR) feature is true?
정답: C
Which three fields are specified when configuring a project contract? (Each correct answer presents part of the solution. Choose three.)
정답: C,D,E
You need to track the project costs in balance accounts until the customer is invoiced.
Which type of project should you use?
Which type of project should you use?
정답: C
Your company invoices in U.S. dollars on a project for a company whose currency is euros.
To avoid any issues with currency exchange rate fluctuations,you agree on a fixed currency exchange rate for invoices.
How should you set up the project?
To avoid any issues with currency exchange rate fluctuations,you agree on a fixed currency exchange rate for invoices.
How should you set up the project?
정답: C
You set up a new internal project that includes work in process (WIP).
You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet.
Which form should you use to specify that each type of cost will be posted to balance accounts?
You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet.
Which form should you use to specify that each type of cost will be posted to balance accounts?
정답: D
You need to configure worker validation project assignments to ensure that certain projects are available for a specific worker.
On which form should you configure this type of validation?
On which form should you configure this type of validation?
정답: B
Which statement for both the cost and the time project types is true?
정답: C